Annual Road Reseal

Fiona2.JPEG

road reseal.jpg

2024 Reseal Program

Minor traffic delays can be expected on the roads listed below whilst reseal works are undertaken.

Works will commence Monday 2 December and are expected to be complete by Friday 20 December 2024.  

Edi

Works scheduled for Monday 2 December 2024.

  • Edi-Cheshunt Road – from Porters Lane to Whites Lane

Milawa

Works scheduled for Tuesday 3 December 2024.

  • Milawa-Bobinawarra Rd - from Oxley Flatts Road to Brown Brothers Winery

Glenrowan

Works scheduled for Tuesday 3 December 2024.

  • Boundary Road – from Church Street to Siege Street
  • Siege Street - from Bridge to Boundary Road

Oxley Township

Works scheduled for Wednesday 4 December 2024.

  • Macartney Street 
  • Ely Street
  • King Street
  • Smith Street

Wangaratta Township

Works scheduled for Thursday 5 December 2024.

  • Braithwaite Street - from Moran Ct to O'Callaghan Drive
  • Orkney Street - from Appin Street to Scott Street
  • Wylie Street – Full length
  • Sisely Avenue – Phillipson Street to Dodsworth Street
  • Larking’s Street – from Muntz Steet to Orr Street

Works scheduled for Friday 6 December 2024.

  • Hay Avenue – Newman to Bullivant Street
  • Bullivant Street

Cheshunt

Works scheduled for Friday 6 November 2024.

  • King Valley Road & Car Parking - front of the General Store

Everton

Works scheduled for Saturday 7 December 2024.

  • White Post Road – from Great Alpine Road to Bennetts Lane

Myrrhee

Works scheduled for Monday 9 & Tuesday 10 December 2024. 

  • Boggy Creek Road - from Redcamps Bridge to Benalla Whitfield Road

 

For information on a list of current road works please refer to Road works Rural City of Wangaratta